Temporary road under construction at the Trans Mountain terminal in Burnaby to bring in components for 14 additional storage tanks. (Trans Mountain)

Trans Mountain pipeline work proceeds with COVID-19 restrictions

25 km of pipe laid in Alberta, Burnaby tank farm expanding

With half of the 50-km Edmonton-area portion of the Trans Mountain pipeline twinning completed, work is continuing to add 14 storage tanks to its Burnaby terminal and expand the Westridge marine terminal for export of Alberta oil sands crude.

Worksite restrictions for COVID-19 on the project now include temperature testing people entering the sites, staggering work shifts to minimize the number of workers on site, and restricting vehicle transport for physical distance, the now-federally owned Trans Mountain said in a project update this week.

Much of the pipeline twinning work from Alberta to the B.C. border has been completed over the past decade, and nearly 25 km of twin pipe has been laid in the Edmonton area. At the west end of the 67-year-old oil and fuel transportation system, piledriving and construction of the shipping terminal expansion into Burrard Inlet are ongoing.

The expansion project includes a total of 19 more storage tanks, with four at Edmonton one at Sumas, where a branch line has served Washington refineries since 1954.

The marine terminal expansion includes a new dock complex with three tanker berths, to allow the loading of three Aframax-size tankers at once. The expansion includes a utility dock to moor tugboats, boom boats and emergency response vessels, added delivery pipelines and an extension of the land along the shoreline to accommodate new equipment.

The foreshore expansion is being constructed of steel retaining walls, which have been filled with aggregate material and soil to establish the foundation.

At the Burnaby terminal, a temporary road is under construction and the site is being prepared for 14 new storage tanks. The plan includes a tunnel through Burnaby Mountain from the tank farm to the Westridge terminal, big enough to contain three 30-inch delivery pipes to load vessels.

With the only pipeline link between Alberta, B.C. and Washington state oversubscribed and increasing shipments by rail before the current pandemic slowdown and turmoil in the world oil market, the expansion pipe is planned to carry heavy oil for export. The existing line will carry refined fuels, light crude and synthetic crude produced from bitumen at upgraders the Edmonton region.

RELATED: Lack of pipelines costing Canada billions, study finds

RELATED: Trans Mountain expansion cost jumps by 70%

The Justin Trudeau government took over the pipeline in 2018 after Kinder Morgan Canada set a deadline to walk away from the expansion project. The $4.5 billion purchase price came with an estimate of $7.4 billion to complete the expansion, an estimate later raised to $12.6 billion with a completion date pushed to 2022 amid protests and court challenges.

A 2018 study estimated Canada was losing nearly $16 billion in revenue that year due to pipeline bottlenecks that effectively made the U.S. the only customer for new capacity.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC politicsCoronavirusTrans Mountain pipeline

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

VIDEO: Townhouse fire in Langley

Crews called to scene Saturday afternoon

VIDEO: Langley-Aldergrove MP Tako van Popta hands out seedlings at Home Depot

Free Saskatoon berry and Red-twig Dogwood plants were offered up to shoppers Saturday morning

VIDEO: Friday night car show a no go at Surrey/Langley border

Vintage cares were turned away at 2800 block of 192nd Street due to COVID-19 precautions

Graduation 2020: Langley Fine Arts student celebrates amid social distancing

Emilie Colbourne submitted a photo of her daughter celebrating grad with her grandparents

Trudeau offers $14B to provinces for anti-COVID-19 efforts through rest of year

Making a difference in municipalities is a pricey proposition

Facing changes together: Your community, your journalists

Thanks for helping the Langley Advance Times to continue its mission to provide trusted local news

‘Like finding a needle in a haystack’: Ancient arrowhead discovered near Williams Lake

The artifact is believed to be from the Nesikip period between 7,500 BP to 6,000 BP

Indigenous families say their loved ones’ deaths in custody are part of pattern

Nora Martin joins other Indigenous families in calling for a significant shift in policing

Friends, family mourn Salt Spring Island woman killed in suspected murder-suicide

A GoFundMe campaign has been launched for Jennifer Quesnel’s three sons

Run for Water: Abbotsford man raises $100,000 running 100-mile marathon

Kevin Barata ran up and down Ledgeview Trails 32 times, exceeding elevation of Mt. Everest

PHOTOS: Anti-racism protesters gather in communities across B.C.

More protests are expected through the weekend

Indigenous chief alleges RCMP beat him during arrest that began over expired licence plate

Athabasca Chipewyan Chief Allan Adam calling for independent investigation

‘I’m pissed, I’m outraged’: Federal minister calls out police violence against Indigenous people

Indigenous Minister Marc Miller spoke on recent incidents, including fatal shooting of a B.C. woman

Most Read