Site C work camp construction nears completion in April 2016. Called Two Rivers Lodge, the camp cost $470 million to build and operate and is a self-contained community with an 800-seat dining room, hair salon, gym, movie theatre and private room accommodations. (B.C. Hydro)

Environmental groups slam NDP decision to continue with Site C

Construction industry, meanwhile, is cautiously optimistic about how the project will look

Environmental groups denounced Premier John Horgan as he announced Monday the province would continue to build the Site C dam.

The Wilderness Committee told Black Press they were “massively disappointed” with what they called the NDP’s “flip-flopping” on the now-$10.7-billion northern B.C. megaproject.

“We can only come to the conclusion that Horgan was lobbied extensively by some of the construction unions,” said national campaign director Joe Foy.

READ: Site C dam goes ahead, cost estimate now up to $10.7 billion

According to the organization, the Site C dam could flood 83 kilometres of the Peace River from near Fort St. John upstream to Hudson’s Hope, contaminating fish stocks, and remove farmland from the Agricultural Land Reserve.

Foy took issue with the province’s claim that it would have cost $4 billion to halt the project, as well as Horgan’s stance that that money could not be paid back over time.

“We believe that is grossly overestimated,” he said. “All that dam can do, unlike the hole in the ground which just sits there, is lose us hundreds of millions of dollars every year it operates.”

He said the NDP’s decision could change B.C.’s political landscape as NDP voters who may feel betrayed move away from the party. Horgan had campaigned earlier this year on a promise to review, not kill, the dam, but he had criticized the BC Liberals’ approach to the project in the past.

More lawsuits expected

Court challenges, Foy said, are likely coming both from environmental and First Nations groups.

“I think rolling over First Nations in this way is unacceptable,” he said. “I think we will begin to see the effects of protests.”

Amnesty International called Horgan’s decision “a blatant betrayal of his government’s commitments to uphold the rights of Indigenous peoples.”

The group called foul on the province’s claim that it was too late to stop the project and said the West Moberly and Prophet River First Nations will continue their legal efforts.

‘We are relieved’

Meanwhile, the Independent Contractors and Businesses Association celebrated the thousands of jobs they believe will be kept and created by continuing work on Site C.

Spokesperson Jordan Bateman said all the extra time the NDP government took to have the dam reviewed was unnecessary, only to have Horgan ultimately go forward.

READ: BC Utilities Commission completes Site C report

Bateman said he also doesn’t buy the province’s new $10.7-billion estimated price tag. When it was approved by the then-Liberal government in 2014, the project was estimated at $8.8 billion.

“You have one analysis done in six weeks that says it could run over budget,” he said. “Frankly, the overruns that the NDP are planning for here are going to be caused by the NDP.”


@katslepian

katya.slepian@bpdigital.ca

Like us on Facebook and follow us on Twitter.

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

History made in draw 1 of 2020 New Holland Canadian Junior Championship in Langley

Champion curler Carly Smith is an amputee competing with other able bodied athletes

Olatoke sets new Spartans record in Edmonton

Langley-based university off to a good start at Golden Bear Open

Critter Care calls out conservation officer after dropping off bear cub covered in ice

Ice can be seen in video matted into emaciated bear cub’s fur

LETTER: Langley man suggests seniors deserve more from taxpayers

Seniors who rely on CPP and Old Age Allowance are stretched

‘Like an ATM’: World’s first biometric opioid-dispensing machine launches in B.C.

First-of-its-kind dispensing machine unveiled in the Downtown Eastside with hopes of curbing overdose deaths

Horgan cancels event in northern B.C. due to security concerns, says Fraser Lake mayor

The premier will still be visiting the city, but the location and day will not be made public

B.C. landlord sentenced to two years in jail for torching his own rental property

Wei Li was convicted of intentionally lighting his rental property on fire in October 2017

VIDEO: Highway 1 left looking like winter war zone with dozens of stranded vehicles

Tow-truck driver says 30 vehicles still dot snowy landscape, including one rolled-over dairy truck

PHOTOS: Eastern Newfoundland reeling, search underway for missing man after blizzard

More than 70 centimetres of new snow fell overnight, creating whiteout conditions

Prince Harry, Meghan to give up ‘royal highness’ titles

‘Harry, Meghan and Archie will always be much loved members of my family,’ says Queen Elizabeth II

Canada Post driver in hospital after ice smashes windshield at Massey Tunnel

Incident happened on Richmond side of the Massey Tunnel

Calls for dialogue as Coastal GasLink pipeline polarizes some in northern B.C.

Coastal GasLink is building the 670-kilometre pipeline from British Columbia’s northeast to Kitimat on the coast

Coquihalla, Highway 3 to be hit with freezing rain, sparking warning to commuters

Hard to say when the freezing rain will turn to regular rainfall, Environment Canada says

Most Read