Kicking Horse widening budget up $151 million as bidders invited

Union-only construction adds 5.8% to price of B.C.’s toughest project

B.C.’s transportation ministry is inviting bids to design and build the most difficult highway project in the province’s history, with costs going up, mainly due to union-only construction and engineering changes.

The latest cost estimate for the fourth phase of the Kicking Horse Canyon widening project is $601 million, a $151 million increase since the 2016 project budget. The ministry estimates that $35 million of that is to implement the NDP government’s “community benefits agreement” for public construction projects, requiring worker membership in approved building trades unions.

Other increased costs include additional geotechnical and other engineering work, additional foundation supports for bridges and retaining walls, consultation with Indigenous communities and a bigger contingency fund due to the risk and complexity of the project.

Phase four is four-laning of the final section of Kicking Horse Canyon east of Golden, 4.8 km from West Portal to Yoho Bridge. Construction is slated to begin in the summer of 2020, with completion by the winter of 2023-24.

The cost increase also includes an additional $23 million in interest charges, since the project was initially approved with a $450 million price tag in 2015.

Transportation Minister Claire Trevena emphasized the safety improvement needed in the Kicking Horse Canyon, which has an accident rate three times the average for B.C. highways and areas with effectively no shoulder for vehicles to pull off in an emergency.

RELATED: B.C. Highway 1 widening demanded for decades

RELATED: Single-bridge option chosen for Sicamous section

The average speed for the existing canyon road is 55-65 km/h, causing long backups behind transport trucks and recreational vehicles winding through the scenic route. The objective of the widening is to get the average speed up to 100 km/h as well as enhance safety.

The project will require closure of the Trans Canada Highway from Castle Junction to Golden for an estimated total of 15 weeks. A detour route using Highway 93 and 95 through Radium Hot Springs will add 104 km to the route, approximately an hour and a half of additional travel time.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Langley Then and Now: 1940 school board meeting goes to 2 a.m.

Local history through news stories and old photos

Sunday Stories

Original works by Langley authors are published by Langley Advance Times every weekend

LETTER: Langley neighbourhood needs more trails

Rural qualities that made Langley special being lost in rapid development of Willoughby

VIDEO: Minister reports ‘modest progress’ after blockade talks with First Nation

Wet’suwet’en hereditary chiefs say Coastal GasLink does not have authority to go through their lands

Canadian nurses’ unions warn national standards for coronavirus protection too low

President says safety protocols nationwide are inadequate compared to those in Ontario and other countries

Murder of sex worker exposes Canada’s hypocrisy on prostitution: advocate

A 2014 law made purchasing sex or benefiting from the selling of sex illegal

Wet’suwet’en return to northern B.C. forest road pipeline workers move through: First Nation

Opponents of a pipeline who support the Wet’suwet’en hereditary chiefs have reoccupied camps at centre of arrests

Wet’suwet’en supporters against pipeline block rail tracks in Vancouver, impacting Amtrak

Amtrak services cancelled, turning back at the U.S.-Canada border

Over a dozen birds found mysteriously dead on rural B.C road

Ministry of Agriculture notified of the strange occurrence on No. 4 Road in Abbotsford

BC Ferries gets injunction against demonstrations in solidarity with Wet’suwet’en

The preemptive injunction is a ‘last resort in the interest of public safety,’ spokesperson says

B.C. men arrested after theft of heavy equipment leads to highway blockade

One man surrendered to police while the other was taken into custody the next morning, RCMP say

Most Read