Trans Mountain pipeline through Langley one step closer to reality

Kinder Morgan's controversial project gets NEB approval
50741langleyTANKER
The National Energy Board approved the twinning of Kinder Morgan's Trans Mountain pipeline, with conditions.

 

Kinder Morgan's Trans Mountain pipeline twinning now has the endorsement of the National Energy Board, which has recommended the federal government approve the project subject to a long list of conditions.

A portion of the pipeline cuts through the Township of Langley's Walnut Grove.

Related Story: Trans Mountain considers alternative oil pipeline route through Langley

The tentative green light from regulators was not unexpected – critics say the NEB has never rejected a pipeline proposal outright.

The NEB review panel found the $6.8-billion project is in the national interest, unlikely to cause significant adverse environmental effects, and its benefits outweigh any "residual burdens."

The report did flag significant adverse effects from increased tanker traffic, causing impacts to southern resident killer whales, but it notes marine shipping is projected to increase with or without the pipeline, and tankers would be a small fraction of that.

Wider access to world markets for Canadian oil, government revenues, and thousands of construction jobs were among the benefits listed.

It found there is a very low probability of a serious spill from the pipeline, a tanker, a tank terminal or pump stations, and that risk is acceptable.

The federal government must now meet a December deadline to approve or reject the project.

Meanwhile, following an election commitment by the federal Liberals to revamp and restore trust in the flawed pipeline review process, a three-member panel will conduct new consultations with communities and first nations and advise cabinet. The panel consists of former Tsawwassen First Nation Chief Kim Baird, former Yukon premier Tony Penikett and University of Winnipeg president Annette Trimbee.

Even if Ottawa gives final approval, big hurdles remain.

During NEB hearings, the province said it could not yet support the pipeline because its conditions for new heavy oil pipelines have not been met, particularly for world-class marine spill response.

The province is also required to conduct its own provincial environmental assessment now, after a court ruling that it could not rely on the federal process.

Even if B.C. comes on board – and there has been speculation a deal could involve Alberta agreeing to buy B.C. electricity – the project still faces aboriginal court challenges, a plan by environmentalists to force a referendum using B.C.'s initiative legislation, and the threat of civil disobedience during construction.

The second pipeline would nearly triple Trans Mountain's capacity to 890,000 barrels per day, resulting in a seven-fold increase in tankers plying Vancouver harbour.

While portions of the 1,150-kilometre pipeline route from Alberta to the terminal in Burnaby closely follows the existing pipeline built in 1953, it would follow a largely new route through the Lower Mainland.

That means traversing farmland and neighbourhoods, and in some cases cutting through parks, such as Surrey Bend Regional Park and Bridal Veils Provincial Park near Chilliwack.

Various cities and regional districts lodged their objections at NEB hearings on the project, while other prominent interveners pulled out of the process last summer, denouncing it as rigged in favour of Kinder Morgan.

Conditions

The NEB's recommendation to approve comes with 157 conditions, up from 145 draft conditions previously circulated.

Kinder Morgan would be required to update earthquake analyses, including studies of seismic faults and liquefaction-prone areas.

Another condition requires it to update risk assessments at the Burnaby and Sumas terminals to quantify the risk of a "boil over" fire, flash fires or vapour cloud explosions, as well as any potential "domino effect" from a failure at one storage tank compromising others.

Kinder Morgan must also assess firefighting resources that would respond to its Burnaby terminal or tank farm and consult with affected municipalities.

The NEB is also requiring Trans Mountain to track its greenhouse gas emissions related to construction and operation, and develop a plan to offset the construction emissions.

The review did not consider the downstream effect on climate change from burning oil overseas.

The report also concedes there will be significant increased greenhouse gas emissions from tanker traffic, which can't be offset.

Kinder Morgan would have until Sept. 30, 2021 to begin construction of the pipeline, after which certificates expire. The company aims to start construction in 2017 and finish it by late 2019.

 

 

TRANS MOUNTAIN BY THE NUMBERS

  • 987 kilometres of new pipeline, plus the reactivation of 193 kilometres of existing pipeline
  • 890,000 barrels per day of oil shipping capacity, up from 300,000.
  • 90 per cent of route parallels existing disturbance and doesn't break new ground
  • Three berths for tankers instead of the existing one at Westridge Marine Terminal
  • 157 conditions set by NEB
  • 686 days from start of hearing to the end.
  • 400 interveners and 1,250 commenters part of NEB process