Powerhouse construction at Site C dam on the Peace River, spring 2019. The project’s $10 billion price tag has pushed up B.C. Hydro debt. (B.C. Hydro)

B.C. Hydro applies for rare cut in electricity rates next year

Province wrote off $1.1 billion debt to help reverse rate increase

B.C. Hydro has applied for a rare rate decrease to take effect next spring, before the cost of hydroelectricity to B.C. consumers is forecast to climb again.

Documents released Friday by B.C. Hydro project a rate decrease of just under one per cent, an abrupt change from an upward trend in recent years driven by debt piling up to upgrade aging facilities and build the Site C dam on the Peace River.

The rate decrease is subject to approval by the B.C. Utilities Commission, and would take effect April 1, 2020. It would be followed by a 3.5 per cent rate increase a year later, according to the latest rates forecast.

B.C. Hydro CEO Chris O’Riley cited lower that forecast debt costs, stronger income from Powerex, the utility’s power trading subsidiary, and reduced costs from purchasing independent power.

The B.C. NDP government tried to freeze rates in 2018, but the BCUC rejected its application. Since then it has suspended independent power contract purchases and in Finance Minister Carole James’ latest budget, wrote off $1.1 billion of B.C. Hydro’s deferred debt by transferring it to the provincial debt.

“I’m thrilled that B.C. Hydro is now able to apply for a rate reduction for the first time in decades,” said Energy Minister Michelle Mungall, whose term got off to a rocky start when she promised a rate freeze and couldn’t deliver.

The NDP government moved to suspend B.C. Hydro’s “standing offer program” for independent power projects, after years of characterizing independent power as a key driver in rising costs. Exceptions would be made for Indigenous partnerships to develop power in remote regions that are off the B.C. Hydro grid, Mungall said at the time.

The NDP government produced a controversial report in February, entitled “Zapped,” that said former premier Gordon Campbell’s 2002 push into contracted run-of-river, wind and biomass power will cost B.C. Hydro $16 billion over the next 20 years.

RELATED: NDP’s consultant points finger at private power costs

RELATED: B.C. budget for 2019-20 bails out B.C. Hydro, ICBC

B.C. Liberal energy critic Greg Kyllo said the NDP’s “assault on clean energy producers” was a move to protect the unionized monopoly of B.C. Hydro production.

“British Columbia has been a leader in green tech and clean energy, and the advances we have seen over the past decade have been thanks to entrpreneurs, private businesses and First Nations investing in the future, certainly not government bureaucrats,” Kyllo said.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislature

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

VIDEO: Langley-based Spartans volleyball team sweeps series against Winnipeg

Next up, Spartans semifinal against Thompson Rivers

Langley Chamber of Commerce asks for input on rail blockades

The local business group is asking if local businesses have been impacted

VIDEO: Giants winning streak now stands at 11

Team erased a 5-2 deficit by scoring every five minutes

Lions Clubs donate generous gift to local hospital to help Langley breathe easy

A $56,000 donation is the largest the hospital has received from the Lions Club

HIGHLIGHTS: Day one and two at the 2020 BC Winter Games

Athletes had sunny – but cold – weather to work with in Fort St. John

Tyler Toffoli scores twice, Canucks crush Bruins 9-3

Stecher, Miller each add three points for Vancouver

Zamboni driver, 42, earns NHL win over Maple Leafs

Emergency goalie called into action for Carolina Hurricanes

Governor general says multiple solutions needed for ‘complicated’ overdose issue

Julie Payette met at a fire hall with firefighters and police officers as well as politicians and health experts

Landlord ordered to pay $11K after harassing B.C. mom to move days after giving birth

Germaine Valdez was pressured to move just a few days after giving birth by C-section to her child

Heart attacks strike B.C. husband and wife just over one year apart

Courtenay couple share personal stories to bring awareness to heart month

‘Nothing surprises us anymore:’ U.S. border officials find brain in package

U.S. Customs and Border Protection agents found the brain packed in a glass mason jar in a Canada Post shipment

Fiery collision involving truck closes Highway 1 at Three Valley Gap

Drivers should expect major delays and congestion; estimated time of re-opening is 2 p.m.

B.C., Ottawa sign sweeping 30-year deal for northern caribou habitat

West Moberly, Saulteau co-manage new protection on two million acres

Most Read